India, Dec. 20 -- The Government of India has issued a release:

Period

Outlay

2009-14

Rs.1,171 crore/year

2025-26

Rs.23,778 crore (More than 20 times)

Period

New track Commissioned

Average commissioning of new tracks

2009-14

292 Km

58.4 Km/year

2014-25

2,292 Km

208.36 Km/year (More than 3 times)

SN

Location

Details

1

Bandra Terminus

3 Pit Lines have been completed

2

Mumbai Central

Platform extension for 24 LHB coaches

3

Jogeshwari

2 additional platforms

4

Dadar

1 additional platform

5

Vasai road

6 platforms, 3 pit lines and 5 stabling lines

6

Panvel-Kalamboli

5 platforms, 4 pit lines and 2 sick lines

7

Kalyan

6 platforms and 4 pit lines

8

LTT

4 platforms and 2 pit lines

9

Parel

6 platforms, 5 pit lines, 6 stabling lines

10

Virar

25 stabling lines

11

Dahanu road

11 stabling lines

12

Mira road

25 stabling lines

SN

Name of Project

Cost

1

CSMT-Kurla 5th & 6th Line (MUTP-II) (17.5 km)

891

2

Mumbai Central-Borivali 6th Line (MUTP-II) (30 km)

919

3

Extension of Harbour Line from Goregaon-Borivali (MUTP-IIIA) (7 km)

826

4

Borivali-Virar 5th & 6th Line (MUTP-IIIA) (26 km)

2,184

5

Virar-Dahanu Road 3rd & 4th Line (MUTP-III) (64 km)

3,587

6

Panvel-Karjat Suburban Corridor (MUTP-III) (29.6 km)

2,782

7

Airoli-Kalwa (elevated) Suburban Corridor link (MUTP-III) (3.3 km)

476

8

Kalyan-Asangaon 4thLine (MUTP-IIIA) (32 km)

1,759

9

Kalyan-Badlapur 3rd& 4th line (MUTP-IIIA) (14 km)

1,510

10

Kalyan-Kasara 3rd Line (67 km)

793

11

Naigaon-Juichandra double chord Line (6 km)

176

12

Nilaje-Kopar double chord Line (5 km)

338

13

Kalyan Yard remodeling work

866

Category

No. of sanctioned Projects

Total

Length

Exp.

New Line

11

1,355

234

10,504

Gauge Conversion

02

609

334

4,286

Doubling/ Multitracking

25

3,134

1,792

24,617

Total

38

5,098

2,360

39,407

S.No.

Project

Cost

1

Pune-Miraj-Londa Doubling (467 Km)

4,670

2

Manmad-Jalgaon 3rd line (160 Km)

2,574

3

Jabalpur-Gondia Gauge Conversion (300 Km)

2,005

4

Chhindwara-Nagpur Gauge Conversion (150 Km)

1,512

5

Panvel-Pen Doubling (35 Km)

263

6

Pen-Roha Doubling (40 Km)

330

7

Udhna-Jalgaon Doubling (307 Km)

2,448

8

Mudkhed-Parbhani Doubling (81 Km)

673

9

Bhusawal-Jalgaon 3rd line (24 Km)

325

10

Jalgaon-Bhusawal 4th line (24 Km)

261

11

Daund-Gulbarga Doubling (225 Km)

3,182

S.No.

Name of the project

Cost (Rs. In crore)

1

Gondia-Ballarshah (Chanda Fort) doubling (240 Km)

4,373

2

Hotgi Byepass line (6 Km)

177

3

Panvel-Chouk doubling section (17 Km)

491

4

Panvel-Somtane Chord line and Panvel-Chikhli Chord line (8 Km)

445

5

Miraj Chord line (2 Km)

129

6

Wardha-Balharshah quadrupling (135 Km)

2,226

7

Puntamba-Sainagar Shirdi doubling (17 Km)

227

8

Itarsi-Nagpur 4th line (297 Km)

5,010

9

Chhatrapati Sambhajinagar-Parbhani doubling (177 Km)

2,006

10

Gondia-Dongargarh 4th line (84 Km)

1,985

11

Wardha-Bhusawal 3rd & 4th line (314 Km)

8,199

12

Jalgaon-Bhadli 5th line (9 Km)

114

13

Gondia bypass line (19 Km)

354

14

Jalgaon-Manmad 4th line (160 km)

2,574

15

Bhusawal-Khandwa 3rd & 4th line (131 Km)

3,285

16

Mudkhed-Medchal & Mahbubnagar-Dhone doubling (417 Km)

4,686

17

Chhatrapati Sambhajinagar-Ankai doubling (98 Km)

961

18

Nilaje and Kopar double chord Line (5 Km)

338

19

Mudkhed junction bypass line (3 Km)

62

20

Purna bypass line (3 Km)

72

21

Ankai bypass Line (2 Km)

29

22

Parbhani-Parli Vaijanath doubling (65 Km)

770

23

Latur Road Station bypass line (2 Km)

47

24

Parli-Vaijanath Station bypass line (2 Km)

56

25

Pachora-Jamner gauge conversion with extension upto

955

26

Vadhavan Port-New Palghar doubling (22 Km)

1,423

27

Ahilyanagar-Beed-Parli Vaijnath new line (261 Km)

4,957

28

Baramati-Lonand new line (64 Km)

1,844

29

Wardha-Nanded new line (284 Km)

3,445

30

Indore-Manmad new line (360 Km)

18,529

31

Wadsa-Gadchiroli new line (52 Km)

1,886

32

Jalna-Jalgaon new line (174 Km)

5,804

33

Daund-Manmad doubling (236 Km)

3,037

34

Kalyan-Kasara 3rd line (68 Km)

1,433

35

Wardha-Nagpur 3rd line (76 Km)

698

36

Wardha-Ballarshah 3rd line (132 Km)

1,385

37

Itarsi-Nagpur 3rd line (280 Km)

2,450

38

Rajnandgaon-Nagpur 3rd line (228 Km)

3,545

39

Wardha-Nagpur 4th line (79 Km)

1,137

(in Cr.)

Length

Commissioned

upto Mar'25

(Rs. in crore)

Malkapur (84 Km)

(in Km)

Upto Mar'25 (Km)

(Rs. in Cr.)

Budget allocation during the last five years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Maharashtra is as under:

The details of commissioning/laying of new track falling fully/partly in the State of Maharashtra during 2009-14 and 2014-25 is as under:

Capacity Augmentation works for Mumbai Suburban area

Presently, about 120 originating Mail/Express trains and about 3200 sub urban trains are handled daily in Mumbai area. To increase capacity and improve safety, several steps have been taken by Indian Railways as under:

To increase train handling capacity at various stations in Mumbai area, following works have beencompleted/taken up/planned at various stations:

In addition to above, Platform extension work at 34 stations to accommodate 15 car EMUs have been taken up.

To improve the capacity of rail network in Mumbai suburban area, Mumbai Urban Transport Project (MUTP)-II costing Rs.8,087 crore, MUTP-III costing Rs.10,947 crore and MUTP-IIIA costing Rs.33,690 crore have been sanctioned. These projects include following works in Mumbai Suburban Area:

To enhance passenger carrying capacity, 238 rakes of 12 cars each with doors have been sanctioned under MUTP-III & IIIA at a cost of Rs.19,293 crore. The process for procurement of these rakes has been taken up.

As on 01.04.2025, 38 projects (11 New Lines, 02 Gauge Conversion and 25 Doubling), of a total length of 5,098 Km, costing Rs.89,780 crore, falling fully/partly in Maharashtra, are sanctioned. The summary is as under:-

Details of some of the recently completed projects falling fully/partly in Maharashtra are as under:

Some of the main projects falling fully/partly in the Maharashtra which have been taken up are as under:

Further, construction works on the flagship High speed bullet train project have gathered momentum in Maharashtra. Now 100% land acquisition has been completed. Works of bridges, aqueducts etc. have been taken up.

Western DFC also passes through Maharashtra. About 178 route Km of western DFC is situated in Maharashtra which is about 12% of overall route length of western DFC. 76 Km of this project from New Gholvad to New Vaitarna in Maharashtra has already been commissioned. Balance works have been taken up. Connectivity of WDFC to JNPT will boost the capacity to handle cargo and container traffic from port to Delhi NCR.

During the last three years i.e. 2022-23, 2023-24, 2024-25 and the current financial year 2025-26, 98 surveys (29 New Line, 2 Gauge Conversion and 67 Doubling) of total length 8,603 Km falling fully/ partly in the State of Maharashtra, have been sanctioned.

Railway projects are sanctioned Zonal Railway-wise and not State-wise or Region-wise as Indian Railways' projects may span across State boundaries.

Railway infrastructure projects falling fully/partly in the State of Maharashtra are covered under Central Railway, South Central Railway, South East Central Railway, South Western Railway and Western Railway Zones of Indian Railways. Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway's website.

Sanction of any railway project depends upon many parameters/factors which include the following:

Completion of Railway project/s depends on various factors which include the following: