India, Dec. 18 -- The Government of India has issued a release:
Ministry / Scheme
Activity
Progress
MoRD (PMAY-G)
Houses Sanctioned (No.)
965
Houses Completed (No.)
11
MoHFW (NHM)
MMUs operationalized (No.)
24
MoJS (JJM)
Sanctioned Villages (No.)
96
Saturated Villages (No.)
1
MoWCD (POSHAN 2.0)
AWCs sanctioned (No.)
7
AWCs operationalized (No.)
7
MoE (SSA)
Hostels sanctioned (No.)
4
MoP (RDSS)
HHs sanctioned (No.)
345
HHs electrified (No.)
313
MNRE
HHs sanctioned (No.)
98
MoC (DoT-USOF)
Habitation planned for coverage (No.)
52
Habitations covered (No.)
30
MoTA
MPCs sanctioned (No.)
15
MPCs Completed (No.)
4
VDVKs sanctioned (No.)
7
Business started (No.)
5
Name of Ministry
Activity
Mission Target (2023-2026)
Sanction details
Physical Achievements
M/o Rural Development
Provision of pucca houses
4.90 lakh houses
471300 houses
238133 houses completed
Connecting roads
8000 km road
6951.39 km road
825 Km road completed
M/o Health and Family Welfare
Mobile Medical Units
1000 MMU (733 MMUs sufficient to cover all)
694 MMUs
694 MMUs operationalized
M/o Jal Shakti
Piped Water Supply
19375 Villages
18463 Villages
7712 Villages 100% Saturated
M/o Women and Child Development
Construction and running of Anganwadi Centres
2500
2500 AWCs
2084 AWCs made operational.
M/o Education
Construction and running of hostels
500
500 Hostels
Work started in 111 Hostels.
M/o Power
Energization of unelectrified HHs
145083 HHs
145083 HHs
134102 HHs Electrified
M/o New and Renewable Energy
Households sanctioned under New Solar Power Scheme
As per identificaton of beneficiaries eligible for off-grid
8911 HHs
5814 HHs Electrified
M/o Communications
Installation of mobile towers
Coverage of 4543 habitations
4015 habitations planned for Coverage
2944 Habitations covered
M/o Tribal Affairs
Multipurpose Centers
1000
1000 MPCs
328 completed
Setting up of VDVKs
500
539 VDVKs
450 VDVKs Business Started
# As information provided by Ministry
Replying to an un-starred question today in Lok Sabha the Union Minister of State for Tribal Affairs Shri Durgadas Uikey informed that the details of benefits given under Pradhan Mantri Janjati Adivasi Nyaya Maha AbhiyaN (PM JANMAN) in the State of Kerala, Ministry-wise, since its inception is given in Annexure I.
On 15th November 2023, Hon'ble Prime Minister launched PM JANMAN for socio-economic development of 75 PVTG communities residing in 18 States and one UT. The mission aims to provide basic facilities to improve their socio-economic conditions such as safe housing, clean drinking water and improved access to education, health and nutrition, road and telecom connectivity, electrification of unelectrified households and sustainable livelihood opportunities in 3 years. These objectives are being met through 11 interventions implemented by 9-line Ministries.
In view of the implementation of PM JANMAN, the Ministry of Tribal Affairs through the State Governments/ UT Administration/departments has undertaken habitation level data collection exercise through PM Gati Shakti mobile application to estimate PVTG population figures and infrastructure gaps in order to cover PVTG population residing in villages & habitations under PM JANMAN.
The details of targets and achievements under the PM JANMAN since its inception is given in Annexure II.
To ensure the effective implementation and monitoring of the PM JANMAN, Ministry has been regularly reviewing the implementation with State Governments and District administrations. Further, the State Government is also required to comply with the instructions of Department of Expenditure regarding SNA SPARSH alongwith applicable GFRs. Besides, for monitoring the progress of the works under PM JANMAN, digital dashboard on PM GatiShakti portal has been developed. A Project Monitoring Unit in the Ministry has also been established for monitoring and coordination with Ministries and States / UT. NITI Aayog has conducted an evaluation study in 2025 covering Centrally Sponsored Schemes including PM JANMAN.
Annexure I
PM JANMAN Progress in the State of Kerala (as on 24th November 2025)
Annexure II
PM JANMAN Progress (as on 24th November 2025)
Disclaimer: Curated by HT Syndication.