India, Aug. 4 -- The Government of India has issued a release:
Sl. No.
Common Infrastructure Facility
Approved Cost (Rs. crore)
Expenditure incurred (Rs. in crore)
Status
1
Common Effluent Treatment Plant (CETP), Solid Waste management
49.73
-
Tender released.
2
Incinerator cost
18.00
-
Tender under preparation
3
Cost of Collection & Landfill site
37.00
-
Tender under preparation
4
Storm Water Drain Network
86.71
9.68
12% work completed
5
Common Solvent Storage System, Solvent Recovery & Distillation
30.00
-
Tender under preparation
6
Common Warehouse
-
Tender under preparation
7
Internal Power Distribution Network Within park
65.00
14.26
Tender under preparation
8
Internal Road network, Compound Wall
149.44
15.03
10% work completed
9
Raw, Potable and Demineralised Water
141.95
55.6
60% work completed
10
Steam generation and distribution system
312.30
-
Tender released.
11
Advanced Laboratory Testing Centre
22.73
-
Tender under preparation
12
Emergency Response Centre
20.17
-
Tender under preparation
13
Safety / Hazardous Operations Audit Centre
14.43
-
Tender under preparation
14
Centre of Excellence
110.29
-
Tender under preparation
60.71
Major common infrastructure facilities under implementation include water supply system, power infrastructure, Common Effluent Treatment Plant (CETP) with Zero Liquid Discharge (ZLD), steam generation system, warehouse, centre of excellence, solvent recovery system, emergency response centre and solid waste management facilities.
The present status of physical and financial progress component-wise of the Himachal Pradesh Bulk Drug Park is as under :
Department of Pharmaceuticals (DoP), Government of India has sanctioned an amount of Rs. 1000 crore on 11.10.2022 for development of Bulk Drug Park in Haroli, District Una, Himachal Pradesh under the Scheme for 'Promotion of Bulk Drug Parks' and out of which an amount of Rs. 225 crore has been released on 20.02.2023. The State Government, has also sanctioned an amount of Rs.118.46 crore and released an amount of Rs. 35.53 crore as state share in F.Y. 22-23 towards development of Common Infrastructure Facilities (CIF).
On the basis of representations received from the State Governments concerned, the status of projects, the level of fund utilisation and the anticipated completion of projects in FY2026-27, the tenure of the scheme has been extended up to FY2026-27.
The review of the progress of the Bulk Drug Park being developed in Himachal Pradesh is regularly carried out by the Scheme Steering Committee of the scheme for "Promotion of Bulk Drug Park", Secretary and Joint Secretary in the Department of Pharmaceuticals and by High Powered Committee headed by Hon'ble Minister of Industries, Himachal Pradesh. Primary reasons affecting delay is the grant of Environmental Clearance which has been granted on 25.09.2025, procedural requirement for permission for felling of trees and bids for procurement. The State Government and implementing agencies are closely monitoring project execution and expediting statutory clearances, tendering and award of contracts for critical infrastructure components. Following receipt of Environmental Clearance, project activities have gained momentum, and multiple infrastructure packages are under implementation or advanced stages of procurement to ensure timely completion and operationalization of the park.
This information was given by Minister of State for Chemicals and Fertilizers, Smt. Anupriya Patel, in a written reply in the Rajya Sabha today.